Page 64 - AERB Annual Report 2020
P. 64

Events rated at level 4 and above are termed as   Two signicant events, one each at RAPS-
                  'Accidents'. The accidents at Chernobyl NPP in   5&6 and KKNPP-1&2 were not rated on INES as
                  former USSR (now in Ukraine) in April 1986 and   these were related to industrial safety and had no
                  Fukushima NPPs in Japan in March 2011 were   relevance to nuclear and radiological safety.
                  rated at level 7 on INES. Events rated at levels 1, 2
                  and 3 are called 'Incidents'. The level 0 or below   Table  1.11:  INES  Rating  of  Signicant  Events
                  scale  means  events  that  have  no  nuclear  and   in NPPs Reported during Calendar  Year  (2020)
                  radiological safety signicance.
                                                                        NPPs         INES Rating of Events
                  1.8.1  Signicant  Events  and  INES  rating  w.r.t.
                      NPPs                                                              INES-0     INES-1
                                                                TAPS - 1&2                0          2
                      All  the  signicant  events  reported  were   TAPS - 3&4           2          0
                  reviewed  in  detail  by  AERB  and  measures  to
                                                                RAPS - 1&2                1          0
                  prevent  recurrence  of  such  events  were
                                                                RAPS - 3&4                1          0
                  recommended.
                                                                RAPS - 5&6                3          0

                                                                MAPS - 1&2                4*         0
                  (i)     Signicant    Events  in    NPP    under
                      Construction / Commissioning              NAPS - 1&2                1          1
                                                                KAPS -1&2                 4          0
                      During  2020,  one  signicant  event  was   KGS - 1&2              3          0
                  reported  from  KAPP-3  during  Phase-B       KGS - 3&4                 1          0
                  commissioning of KAPP-3. The signicant event   KKNPP - 1&2             9 *        0
                  was rated at Level-0 on INES of IAEA.         Total                     29         3

                  v      Reactor  Manual  Shutdown due to internal    *  One  event  at  MAPS-2  and  three  events  at
                      seal leak in Primary Circulating Pump-2 at    KKNPP-1&2  were  assigned  provisional  rating
                      KAPP-3                                   of level 0 as these events are still under investigation.

                      KAPP-3  reactor  was  critical  and  Reactor   For  the  purpose  of  analysis,  the  events
                  power was 0.1% FP and stable. PHT temperature   reported during year 2020 were also categorized
                  was  258.6°C  with  all  four  PCPs  running.   as  per  the  IAEA-IRS  coding  system.  The
                  Inadvertent intermittent actuation of PCP-2 back   classication  of  systems  failed/affected  during
                  up seal while PCP-2 was running led to higher   the signicant events is given in Figure-1.2. The
                  vibration and failure of mechanical seal leading to   classication of direct causes and root causes of
                  PCP  internal  leak  and  minor  external  leak.   the signicant events are given in Figure-1.3 & 1.4
                  Signicant event report was reviewed in detail by   respectively.
                  AERB  and  corrective  measures  to  prevent
                  recurrence of such event was recommended.    v    Signicant   Events   Rated  at  Level-1 on
                                                                    INES
                       Direct cause for the SER is attributed to PCP
                  vibration and mechanical seal leak. Root cause of   (i)    On January 8, 2020, TAPS-1 was shut down
                  SER is attributed to un-envisaged design aspect.  for refueling. During the refueling outage, as
                                                                    per  scheduled  In-Service  Inspection  (ISI)
                  (ii)   Signicant Events  in  Operating  NPPs     program, inspection of weld joints of reactor
                                                                    coolant  system  piping  was  carried  out.
                      During the year 2020, a total of 34 signicant   Liquid  Penetration  Test  (LPT)  revealed  a
                  events were reported from operating NPPs. Out     defect  /seepage  in  a  circumferential  weld
                  of these, 25 signicant events were rated at level 0   joint (J-16) in the recirculation loop A piping
                  on INES and three events (one each at NAPS-1,     o f   m a i n   r e a c t o r   c o o l a n t   s y s t e m .
                  TAPS-1  and  TAPS-2)  were  rated  at  level  1  on   Subsequently, the weld joint was examined
                  INES.  4  signicant  events  (one  at  MAPS-2  and   by  ultrasonic  method  and  this  revealed  a
                  three at KKNPP-1&2) were assigned provisional     circumferential crack in Heat Affected Zone
                  rating  of  level  0  since  these  are  still  under   (HAZ)  of  the  weld  joint.  The  detailed
                  investigation.                                    investigations  revealed  that  the  crack  had
                                                                    occurred  due  to  Inter-Granular  Stress
                      The  number  of  SERs  in  operating  NPPs    Corrosion Cracking (IGSCC). The previous
                  along  with  their  ratings  on  INES  are  given  in   inspections  of  the  affected  weld  joint  was
                  Table-1.11.
                                                                                                            30
                                                                                       AERB Annual Report 2020
   59   60   61   62   63   64   65   66   67   68   69