Page 21 - AERB Annual Report 2020
P. 21

Shri G. Nageswara Rao, Chairman, AERB and Dr. A. K. Mohanty, Director,
                                BARC signing an Agreement for Technical and Scientic Support

                 construction  activities  were  initiated  and     Clearance for Excavation to KKNPP-5&6 was
                 remained in progress for safety related buildings.   issued  on  November  14,  2018  with  certain
                 As  part  of  FPC  stipulations,  AERB  carried  out   stipulations. Excavation of main plant area was
                 review  of  design  adequacy  checks  for  critical   completed. Review of analysis reports for safety
                 locations of civil structures following AERB safety   related  buildings  was  completed.  KKNPP-5&6
                 standards, and of concrete mix designs for normal   submitted application for FPC along with PSAR
                 and  heavy  concrete.  Additionally,  NPCIL   and review of the same is in progress.
                 requested for erection of core catcher. The request
                 was reviewed and erection of Core Catcher was       Commissioning activities are in progress at
                 also completed. NPCIL submitted Application for   Prototype    Fast    Breeder    Reactor    (PFBR).
                 Erection  of  Major  Equipment  (MEE)  in  August   Subsequent to AERB clearance, 42 fresh fuel sub-
                 2020 which is under review.                   assemblies (FSA) were received and safely stored
                                                               in  the  storage  facility.  AERB  is  monitoring  the
                                                               aspects  related  to  safe  storage  of  these  FSAs.
                                                               Towards  rectication  of  Large  Rotatable  Plug
                                                               (LRP) bearing, works related to inspection of load
                                                               and  spacer  balls,  greasing,  placing  of  balls  on
                                                               bottom  race  and  top  race  activities  were
                                                               completed.  Further  testing  activities  and
                                                               inspection  of  back-up  seal  in  LRP  were  in
                                                               progress.

                                                                     After  satisfactory  review  of  light  water
                                                               commissioning  activities  and  tests  associated
                             View of KKNPP-3&4                 with moderator and auxiliary systems in Unit-3 of




                                                                                       AERB Annual Report 2020  xvii
   16   17   18   19   20   21   22   23   24   25   26