Page 25 - AERB Annual Report 2020
P. 25
Glimpses of Remote Regulatory Inspection of Radiation Facilities
Phase-B commissioning and preparedness for view of increase in the occupational health safety
Phase-C commissioning activities. related incidents at KKNPP-3 to 6 site.
The details of regulatory inspection of nuclear and Radiation Facilities
radiation facilities during this period are given in
Chapter-3. AERB suspended licence for operation of a
Radiography Institution for one year owing to
Enforcement Actions in Nuclear and Radiation violations of safety requirements and withdrawn
Facilities approval of RSO and Radiographer responsible
for a period for indulging in unsafe industrial
Nuclear Facilities
radiography operations.
One fatal incident of survey boat
Radiation Professional (RP) Certicate was
was reported from KKNPP-3&4 site.
misused by two professionals for obtaining RSO
Subsequently, all construction activities (land
approval to facilitate eight nucleonic gauge
and sea based) of the permanent dyke and ow
institutions for procurement of NG with
training dyke were suspended by NPCIL. AERB radioactive source from one of the NG supplier.
reviewed the incident in detail and based on the
AERB issued warning letters to eight NG
improvements in the safety management system
institutions and concerned supplier for
implemented by Site, permission was granted to
committing improper work practices.
restart land-based construction activities at dyke.
The details of enforcement actions in nuclear and
A letter on 'Enhancement of Safety radiation facilities during this period are given in
Supervision at KKNPP-3 to 6 Site' was issued in
AERB Annual Report 2020 xxi